






|
Projects : Generator
Replacement Electrical Engineering
Florida Crystals
operates one of the largest sugar mills in the U.S. The
plant burns sugar cane mulch to produce process steam
used in the production of raw sugar. Excess steam is used
in the production of 100MW of electricity that is sold to
Florida Power and Light (FP&L). The co-generation
facility went on line in 1994. Following electrical
generator problems that necessitated a
"re-wind", the generator unit soon experienced
a catastrophic failure that resulted in a total loss of
the generator. On behalf of Siemens-Westinghouse Power
Corporation (SWPC), DPT provided electrical engineering
and installation support necessary to replace the failed
generator with a new 165 MVA machine met the owners
tight restart schedule.
While
modern machines are designed to match the existing plant
duty conditions, the output and configuration of the new
machine did not exactly match that of the failed unit
since the new unit was destined for another installation.
Consequently, modifications to various electrical items
were required.

Installation of the
new 165 MVA Generator Unit and 6000A Non-Segregated Bus
DPT engineers worked closely with SWPC engineers to
ensure that the modifications to the existing protective
scheme were properly made to provide proper coordination
between the new generator, the plant distribution system
and the FP&L switchyard interface. We also worked
with local contractors to verify that new generator and
system protective devices were properly set and that a
new generator control system was functioning properly
because the new unit had a different excitation system
than the original. DPT provided oversight to the
manufacture and installation of a new 6000A
non-segregated bus that was installed from the generator
to the generator breaker. The main leads of the
replacement generator exited the unit 90° from the
existing unit which required that DPT engineers design
and oversee installation of a new main lead cubicle.
Completion of the work allowed the unit to return to
service approximately 10 weeks after the initial project
authorization.
|
Projects:
Studies and Development
Site-Civil
Development
Structural Engineering
Mechanical Engineering
Electrical Engineering
OEM Analytical Support
|